At A.W. Oakes & Son, taking on complex, large-scale civil construction is built into our foundation. Since the summer of 2025, Project Managers Brian Rucka and Mike Newholm have been leading A.W. Oakes & Son's field operations at the Oak Creek generating site, executing site preparation and utility infrastructure for a multi-year energy transformation.
Spanning three years with completion targeted for early 2028, the scope covers two distinct construction sites under one larger umbrella:
- Oak Creek Combustion Turbine (OCCT) Site: ~25 acres
- Liquefied Natural Gas (LNG) Site: ~17 acres
Together, these facilities represent a significant investment in regional energy reliability, and A.W. Oakes & Son is proud to serve as a foundational civil partner on the ground.

The Scope: Heavy Earthwork & Critical Underground Reroutes
Building next-generation power generation facilities on an active utility property requires far more than standard earthmoving. A.W. Oakes & Son is handling comprehensive sitework across both footprints, including mass grading, trench excavation, structural backfilling, and final site surface treatments.
One of the biggest civil challenges on an active site with decades of history is working around existing underground utilities.
"Because these new facilities are being constructed on existing utility property, existing underground utility exploration has been a major scope and focus for our team," explains Brian Rucka, A.W. Oakes & Son Project Manager. "Before any excavation can begin, we perform detailed utility exploration to locate legacy lines. To keep the active power plants running without interruption, we’ve coordinated and executed major utility reroutes—including domestic and fire protection water mains, sanitary sewer, electric power, fiber optics, and gas mains."
2026 Milestones: Preparing the Subgrade Before Winter
As the project enters its second season, the team is making steady progress toward critical subgrade milestones.
With underground utility trenching and major structural concrete work wrapping up, the primary focus for 2026 is completing site mass structural backfilling and bringing both sites to rough-grade elevation prior to winter weather. Achieving these elevations sets the stage for the final 2027 phase, which will focus on above-ground site finishes, asphalt paving, fencing, landscaping, and signage.

Daily Operations in an Active Utility Environment
Operating on an active utility campus demands a level of safety, communication, and logistical coordination far beyond a standard greenfield jobsite.
With hundreds of craft workers and multiple trade contractors on-site daily, close communication between field supervision, plant operators, and site management is mandatory.
"Daily operations come down to constant coordination," says Rucka. "Every day, we have major oversized equipment and material deliveries arriving that need to be sequenced with all trades. Additionally, heavy crane lifts and utility testing procedures require daily safety exclusion zones that restrict work areas. Morning and evening alignment meetings keep everyone on the same page and keep the site running safely."
Building for the Future
The OCCT and LNG projects at Oak Creek showcase the technical discipline, safety focus, and collaborative spirit that define A.W. Oakes & Son. Under the direction of Mike Newholm and Brian Rucka, our crews are proud to hit our 2026 milestones as we help lay the groundwork for the region’s energy future.